Technical and economic study of striking and clearing operations in buildings under construction. Case study in Bogotá, Colombia

Estudio técnico económico de los procesos de cimbrado y descimbrado en edificaciones. Estudio de caso en Bogotá, Colombia

DOI:

https://doi.org/10.15446/dyna.v83n199.56086

Palabras clave:

New Simplified Procedure, shores, time estimations, load estimations, estimation of personnel and equipment costs (en)
Nuevo Procedimiento Simplificado, puntales, estimación de tiempos, estimación de cargas, estimación costos personal y equipo. (es)

Autores/as

This paper evaluates the economic benefits of shorter construction times that can be attained by applying the New Simplified Procedure (NSP) in multi-storey buildings. The reference building was a multi-storey residential reinforced concrete framework structure with one-way slabs located in Bogotá, Colombia. The study was divided into different phases including the characterization of the components, a study of the different methods to determine load transmissions between slabs and shores, and a review of the cost of renting shoring and formwork materials and labor costs for the building under study. After applying the procedure, an economic assessment was carried out on the execution times obtained in each of the operations studied. The analysis of the construction process of the building structure using the NSP showed that considerable savings can be achieved in construction times without any risk for the integrity of the structure.
El presente artículo evalúa el beneficio económico de la aplicación del Nuevo Procedimiento Simplificado (NPS), reflejado en los plazos de construcción en edificaciones de entrepisos sucesivos. El edificio de referencia corresponde a un edificio residencial resuelto con pórticos y entrepisos en una dirección, de concreto reforzado ubicado en la ciudad de Bogotá. Las fases desarrolladas en cumplimiento del objetivo planteado, constaron de una caracterización de los componentes, el estudio de distintas alternativas para determinar la transmisión de cargas entre entrepisos y puntales, y una revisión de los precios de alquiler de equipo auxiliar y personal del edificio de referencia. Aplicando dicho procedimiento se realizó una evaluación económica de los plazos obtenidos en cada una de las operaciones estudiadas. Se destaca que el análisis del proceso constructivo de la estructura de la edificación empleando el NPS permite lograr ahorros considerables en la ejecución de la edificación sin poner en riesgo la integridad de la estructura.

Referencias

Estudios económicos CAMACOL, Evolución de las normas técnicas y la inclusión de nuevos sistemas constructivos. Revista Coordenada Urbana. 44, Diciembre, 2012.

Estudios Económicos CAMACOL, Tendencia reciente de los costos en construcción de vivienda en Colombia. Revista Coordenada Urbana. 31, Octubre 2011.

Grundy, P. and Kabaila, A., Construction loads on slabs with shored formwork in multistory buildings, ACI Structural proceedings, 60(12), pp. 1729-1738, 1963.

Stivaros, P. and Halvorsen, G., Equivalent frame analysis of concrete buildings during construction, Concrete International, 13(8), pp. 57-62, 1991.

Duan, M.Z. and Chen, W.F., Improved simplified method for slab and shore load analysis during construction. Project report CE-STR-95-24, Purdue University, West Lafayette, Ind., USA, 1995.

Moragues, J.J., Catalá, J. and Pellicer, E., An analysis of concrete framed structures during the construction process, Concrete International, 18(11), pp. 44-48, 1996.

Rosowsky, D.V., Philbrick, T.W. and Huston, D.R., Observations from shore load measurements during concrete construction. Journal of Performance of Constructed Facilities, 11(1), pp. 18-23, 1997. DOI: 10.1061/(ASCE)0887-3828(1997)11:1(18)

Fang, D.P., Zhu, H.Y., Geng, C.D. and Liu, X.L., Floor load distribution in reinforced concrete buildings during construction. ACI Structural Journal, 98(2), pp. 149-156, 2001. DOI: 10.14359/10183

Alvarado, Y.A., Calderón, P.A., Gasch, I. and Adam, J.M., A numerical study into the evolution of loads on shores and slabs during construction of multistorey buildings. Comparison of partial striking with other techniques, Engineering Structures, 32(10), pp. 3093-3102, 2010. DOI: 10.1016/j.engstruct.2010.05.028

Calderón, P., Alvarado, Y.A. and Adam, J.M., A new simplified procedure to estimate loads on slabs and shoring during the construction of multistorey buildings, Engineering Structures, 33(5), pp. 1565-1575, 2011. DOI: 10.1016/j.engstruct.2011.01.027

Gasch, I., Estudio de la evolución de cargas en forjados y estructuras auxiliares de apuntalamiento durante la construcción de edificios de hormigón in situ mediante procesos de cimbrado, clareado y descimbrado de plantas consecutives, PhD Tesis, Universitat Politècnica de València, Valencia, Spain, 2012. [En línea]. Disponible en: http://hdl.handle.net/10251/15407

Gasch, I., Alvarado, Y.A., Calderón, P.A. y Torres, B., Transmisión de cargas entre forjados y puntales en un edificio de forjado reticular de casetón perdido utilizando clareado, Informes de la Construcción, 65(530), pp. 195-202, 2013. DOI: 10.3989/ic.12.046

Gasch, I., Alvarado, Y.A., Calderón, P.A. and Ivorra, S., Construction loads using a shoring-clearing-striking process, Proceedings of ICE Structures and Buildings, 167(SB4), pp. 217-229, 2014. DOI: 10.1680/stbu.12.00006

Scanlon, A. and Murray, D.B., Practical calculation of two-way slab deflection, Concrete international, 4(11), pp. 43-50, 1982.

Ministerio de Ambiente, Vivienda y Desarrollo, Reglamento colombiano de construcción sismo resistente NSR-10, Bogotá D.C., Colombia, 2010.

ACI Committee 347. ACI 347.2R-05: Guide for shoring/reshoring of concrete multistory buildings. American Concrete Institute, Farmington Hills, MI, USA, 2005.

Calavera, J. and Fernández, J., Cuaderno Nº 3: Criterios para el descimbrado de estructuras de hormigón, Madrid: INTEMAC, 1991.

Alvarado, Y.A., Estudio experimental y numérico de la construcción de forjados hormigonados in situ mediante procesos de cimbrado, clareado y descimbrado de plantas consecutives, PhD Tesis,

Universitat Politècnica de València, Valencia, España, 2009. [En línea]. Disponible en: http://hdl.handle.net/10251/7285

Dimensions

PlumX

Visitas a la página del resumen del artículo

596

Descargas

Los datos de descarga aún no están disponibles.

Cómo citar

[1]
“Estudio técnico económico de los procesos de cimbrado y descimbrado en edificaciones. Estudio de caso en Bogotá, Colombia”, DYNA, vol. 83, no. 199, pp. 102–107, Oct. 2016, doi: 10.15446/dyna.v83n199.56086.