Probabilistic sensitivity of the cost of earth moving to the variation of operating conditions
Sensibilidad probabilística del costo de movimiento de tierras a la variación de las condiciones de operación
DOI:
https://doi.org/10.15446/dyna.v86n210.77278Palabras clave:
Earthmoving, construction equipment, road construction, construction cost (en)Movimiento de tierras, equipos de construcción, construcción de carreteras, costos de construcción (es)
The construction comprises a wide spectrum of variables that need to be analyzed to carry out an adequate project planning to generate profit and to comply with the project technical specifications. The objective of this research is to study the variation of costs in earthworks according to the operating conditions of the construction equipment. The sensitivity of production and production costs to the variation of the operating conditions of the construction equipment were analyzed through a probabilistic model. The effect of variations on the parameters involved in the calculation of earthwork production were analyzed for the hauling equipment in different operating scenarios.
La construcción comprende un amplio espectro de variables que requieren ser analizadas para realizar una adecuada planeación, para generar utilidades y cumplir con las especificaciones del proyecto. Esta investigación tiene como objetivo estudiar la variación de los costos en los movimientos de tierras según las condiciones de operación de los equipos, se analiza mediante un modelo probabilístico la sensibilidad de la producción y los costos de producción a la variación de las condiciones de operación de los equipos para movimiento de tierras. Se investiga el efecto las variaciones en los parámetros involucrados en el cálculo de la producción en diferentes escenarios de operación de los equipos de acarreo del material excavado.
Referencias
Golparvar-Fard, M., Heydarian, A. and Niebles, J. Vision-based action recognition of earthmoving equipment using. Advanced Engineering Informatics, 27 (4), pp. 652-663, 2013. www.elsevier.com/locate/aei
Peurifoy, R.L., Schexnayder, C.J. and Shapira, A. Construction planning, equipment, and methods. India: McGraw-Hill Education, 2006.
Ramírez-Cardona, E. Efectos de la incertidumbre, asociada a la estimación de duraciones de actividades, en la programación de proyectos de construcción de infraestructura vial., Trabajo de grado, Escuela de Ingeniería Civil y Geomática, Universidad del Valle, Santiago de Cali, Colombia, 2014.
Okmen, O., and Ozkas, A. Scenario based evaluation of a cost risk model through sensitivity analysis. Engineering, Construction and Architectural Management, 22 (4), pp. 403-423, 2015. http://dx.doi.org/10.1108/ECAM-09-2014-0121
Berger, E., Gambini, I., and Velásquez, C., Simulación de sistemas. Perú: Instituto de investigación en ciencias matemáticas, 2000.
Cámara Colombiana de la Infraestructura, Tarifas de arrendamiento para equipos de construcción, Colombia, 2010, 31 P.
Cómo citar
IEEE
ACM
ACS
APA
ABNT
Chicago
Harvard
MLA
Turabian
Vancouver
Descargar cita
Licencia
Derechos de autor 2019 DYNA

Esta obra está bajo una licencia internacional Creative Commons Atribución-NoComercial-SinDerivadas 4.0.
El autor o autores de un artículo aceptado para publicación en cualquiera de las revistas editadas por la facultad de Minas cederán la totalidad de los derechos patrimoniales a la Universidad Nacional de Colombia de manera gratuita, dentro de los cuáles se incluyen: el derecho a editar, publicar, reproducir y distribuir tanto en medios impresos como digitales, además de incluir en artículo en índices internacionales y/o bases de datos, de igual manera, se faculta a la editorial para utilizar las imágenes, tablas y/o cualquier material gráfico presentado en el artículo para el diseño de carátulas o posters de la misma revista.